Public Procurement and Asset Disposal Act CAP. 412C

Section 145 of Public Procurement and Asset Disposal Act CAP. 412C: Recovery of the performance Security

(1) The performance security shall be returned to the successful tenderer within thirty (30) days following the final acceptance by the accounting officer of the procuring entity.
(2) For the avoidance of doubt, the thirty (30) days referred to in subsection (1) above shall include the retention period except in cases of procurement for works where the period shall commence from the date of practical completion or handover, whichever is earlier.

Check the current authoritative text and amendment history before relying on this provision.

View all provisions of Public Procurement and Asset Disposal Act CAP. 412C →

Continue through this Act

View all →

Section 146 — Advance payment

No works, goods or services contract shall be paid for before they are executed or delivered and accepted by the accounting officer of a procuring entity or an officer authorized by him or her in writ…

Section 148 — Use of advance payment

The successful tenderer shall use the advance paid only in activities related to the tender. If the successful tenderer uses the entire advance or part of it in other activities that are unrelated to…

Section 149 — Sub-contracting

(1) If the tender documents do not prohibit subcontracting, the successful tenderer may subcontract part of the tender but only if the person to be subcontracted has not been debarred from procurement…

Section 150 — Contract administration

(1) An accounting officer or his or her appointed representative shall be responsible for ensuring that the goods, works and services are of the right quality and quantity. (2) The head of the procure…