Public Procurement and Asset Disposal Act CAP. 412C

Section 149 of Public Procurement and Asset Disposal Act CAP. 412C: Sub-contracting

(1) If the tender documents do not prohibit subcontracting, the successful tenderer may subcontract part of the tender but only if the person to be subcontracted has not been debarred from procurement proceedings in accordance with this Act or has participated in the procurement of goods, works or services related to that contract.
(2) The successful tenderer shall be responsible towards the procuring entity for the obligations of the sub-contractor.

Check the current authoritative text and amendment history before relying on this provision.

View all provisions of Public Procurement and Asset Disposal Act CAP. 412C →

Continue through this Act

View all →

Section 150 — Contract administration

(1) An accounting officer or his or her appointed representative shall be responsible for ensuring that the goods, works and services are of the right quality and quantity. (2) The head of the procure…

Section 152 — Contract monitoring

The head of the procurement function shall prepare monthly progress reports of all procurement contracts of the procuring entity and submit them to the accounting officer.

Section 153 — Termination of contract

(1) Upon the request of the procurement management unit, the accounting officer of a procuring entity may approve the request for termination of contract. (2) A contract document shall specify the gro…

Section 154 — Contract close out

An accounting officer of a procuring entity shall close out a procurement contract immediately after completion and the close out shall involve the following— (a) the head of procurement function shal…