Public Procurement and Asset Disposal Act CAP. 412C

Section 140 of Public Procurement and Asset Disposal Act CAP. 412C: Interest on overdue amounts and liquidated damages

The following shall apply with respect to delayed performance and overdue amounts owed by a procuring entity and a contractor under a contract for a procurement —
(a) unless the contract provides otherwise, the procuring entity shall pay interest on the overdue amounts;
(b) the contractor shall be liable to liquidated damages for delayed performance;
(c) the interest and liquidated damages to be paid under paragraph (a) and (b) shall be in accordance with prevailing mean commercial lending rate as determined by Central Bank of Kenya; and
(d) the methods of computing interest liquidated and ascertained damages shall be as prescribed in the regulations.

Check the current authoritative text and amendment history before relying on this provision.

View all provisions of Public Procurement and Asset Disposal Act CAP. 412C →

Continue through this Act

View all →

Section 142 — Performance Security

(1) Subject to the regulations, a successful tenderer shall submit a performance security equivalent to not more than ten per cent of the contract amount before signing of the contract. (2) In case th…

Section 143 — Nature of performance security

The performance security may not generate interest and it shall be determined in accordance with the form provided for in the tendering document and may be paid in form of a bank guarantee, issued by…

Section 146 — Advance payment

No works, goods or services contract shall be paid for before they are executed or delivered and accepted by the accounting officer of a procuring entity or an officer authorized by him or her in writ…

KEEP THE USEFUL PART

Save to My Research

Create a new folder