Section 54 of Public Procurement and Asset Disposal Act CAP. 412C: Procurement pricing and requirement not to split of contracts
(1) No procuring entity may structure procurement as two or more procurements for the purpose of avoiding the use of a procurement procedure except where prescribed.
(2) Standard goods, services and works with known market prices shall be procured at the prevailing market price.
(2A) The head of the procurement function shall carry out market surveys to inform the placing of orders or decision making on a procurement by the relevant awarding authority.
(2B) For infrastructure projects the head of the procurement function in liaison with the head of the technical function in a procuring entity shall, prepare a market survey at the beginning of every financial year of the cost of goods and services and thereafter prepare a current cost handbook to be revised every six months for use in the decision making in the procurement process by the procuring entity.
(3) The Authority shall issue a quarterly market price index as reference guide to assist accounting officers make informed price decisions.
(4) Public officers involved in transactions in which standard goods, services and works are procured at unreasonably inflated prices shall, in addition to any other sanctions prescribed in this Act or the Regulations made thereunder, be required to pay the procuring entity for the loss resulting from their actions.
[Act No. 32 of 2022 , s. 14.]